Editing Float
In the Open Standard
Mohamed CivilMember for 10 years 5 months
- Created
- 3
- 2
0
Please someone help me..
I have been creating a baseline for a high rise building project(Contract period is 2 years).I found that many activties have more than 200 days float and some activties have -1 (Minus one day) float. Although project completion date has come to correct finishng date.
Please someone help me as soon as possible by telling advice to reduce the float(Contract document indicates as maximum allowable float is 60 days)