Restriction on Activity

Pulkit VermaMember for 12 years 3 months
Created
1
1
0

Hi Experts,

In My project, I need to assign Project Manager in particular activity then after baseline project move from P6 to EBS.

but many times it happen that PM are not assigning themself to that activity.

Is there any way that I can put restriction that if PM (Labor resource) not assigned on particular task then A warning message flashed on screen saying that " you have not assigned Project Manager on this project ".

I Understand this is business process but though If there is any validation for this then It will be great for me.

 

Pulkit Verma

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi PulkitThe simple way is to

    Hi Pulkit

    The simple way is to form a hammock summary for all the tasks that need PM resource and then add it to the summary bar.

    That way you will cover the gaps over the deployment period.

    This method works with all non driving support resources such as tower cranes and batching plants.

    Best regards

    Mike Testro