Link between remaining duration and % complete
In the Open Standard
Kamesh AvasaralaMember for 15 years 11 months
- Created
- 5
- 2
0
Dear All,
iam using P6 latest version , after i updated activities when i update % automatically remaining dutaion changing visa versa.
but i want to enter both seperate like % 20 and RD 10 days not able to do if i chage % will automatiacally RD, again if i change RD will changing the % , but in older version of primavera P3 there is an option link remaining duration to % complete. but in latest P6 version i didnt find that in latest version can any body help in this regard.
kamesh
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?