Link between remaining duration and % complete

Kamesh AvasaralaMember for 15 years 11 months
Created
5
2
0

Dear All,

iam using P6 latest version , after i updated activities when i update % automatically remaining dutaion changing visa versa.

but i want to enter both seperate like % 20 and RD 10 days not able to do if i chage % will automatiacally RD, again if i change RD will changing the % , but in older version of primavera P3 there is an option link remaining duration to % complete. but in latest P6 version i didnt find that in latest version can any body help in this regard.

 

kamesh

5 replies

Oldest first
  1. 0
    David Kelly ·

    Kamesh, This is a HUGE

    Kamesh,

     

    This is a HUGE subject, especially if you come from a P3 background.

    In p6 "duration % complete" = RD

    You will almost certainly want to change to Physical % complete...... but that is only the start of the story.

  2. 0
    Zoltan Palffy ·

    There is no switch in P6

    There is no switch in P6 David hit the nail on the head you will have to use physical % comeplete if you do not want the % to update the remining duraiton or vice versa. 

    Since there is no switch if you use DURATION % complete it must update the remaining duration and vice versa

  3. 0
    Kamesh Avasarala ·

    Dear All,Thank you for reply

    Dear All,

    Thank you for reply i will use physical % only but now i already assign as duration % complete can i chage it to physical % complete? 

  4. 0
    Kamesh Avasarala ·

    Dear All,Thank you for reply

    Dear All,

    Thank you for reply i will use physical % only but now i already assign as duration % complete can i chage it to physical % complete? 

  5. 0
    Zoltan Palffy ·

    Changing duration type from

    Changing duration type from duration % complete to physical % complete is a 3 step process. 

    1st filter for ALL activities then add a column and expand General category and select duration type

    now in the duration type column select Percent complete and then do a fill down (this changes the duration % complete type for all EXISTING activities to Physical % Complete).

    2nd go to the Projects directory and make sure that your project is highlighted click on the Defaults tab and change the Percent Complete Type to Physical (this changes the duration % complete type for all NEW activities to Physical % Complete).

    3rd go to tools global change and NEW on the right hand side.

    up top under Select Subject Area make sure that it is Activities then add this specification

    Where           Duration % Compete       is greater than          0

    Then

    Physical % Complete       =         Duration % Complete

     

    then select change then lower right select Commit Changes

    Done 