Move labor resouce from one activity to another - resource assignment reallocation

Chris RadeckiMember for 21 years 5 months
Created
3
2
0

in P6 R8.3.6,  I want to move various labour resources on various activities to other existing activities.   Some of the resources have been wrongly allocated, others need to move to a different time period. 

I want to move the resources with the associated Resource Assignment UDF's.

Is there a way that I can drop and drag the resource and assigned codes from one activity to another in Resource Assignment Tab (similar to task drop and drag in Activities table)? 

Or can I do it some other way - drop and drag/ copy &  paste?

Plan B is to reassign using excel export/import  (create and delete) - or is this the only way to do it without SQL access?

Thanks

 

 

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    plan B is your answer

    plan B is your answer

  2. 0
    Chris Radecki ·

    ZoltanAppreciate the quick

    Zoltan

    Appreciate the quick reply.  Will proceed on this basis. 

    Would be nice to have in Primavera 9.

  3. 0
    Chris Radecki ·

    ZoltanAppreciate the quick

    Zoltan

    Appreciate the quick reply.  Will proceed on this basis. 

    Would be nice to have in Primavera 9.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?