Which Primavera P6 Percent Complete Type to Use?

Emily FosterMember for 15 years 2 months
Created
2
2
0

Primavera P6 has three different ways to track schedule progress. Here we explore the best applications for each type  http://ow.ly/Mxpq302V5DS

2 replies

Oldest first
  1. 0
    David Kelly ·

    Simple: If you are an Owner

    Simple:

     

    If you are an Owner who employs contractors,  you use Duration

    If you are one of those contractors, you use Physical (the only way to keep Earned Value, Remaining Duration, and Remaining units independent)

    If you are the victim of a cruel medical experiment, you use Units

  2. 0
    Emily Foster ·

    Hi David - Love it!

    Hi David - Love it!