Resource and cost Allocation

Mohamed CivilMember for 10 years 5 months
Created
7
3
0

Can you please tell me how to assign cost and resources in very fast way in Primavera P6?

Someone told me assigning in excel and importing into primavera P6 is the easiest method in order to do resource or cost allocation.I don't know how to perform that.Please someone tell me the procedure of that.

If you have any easier methods to assign resources and cost,please tell me.

I'll be thankful for you for your sharing...

Please explain the procedure in step by step

7 replies

Oldest first
  1. 0
    Mohamed Civil ·

    Please,Can anyone hlp me by

    Please,Can anyone hlp me by sharing his/her experience with me regarding the above question??

  2. 0
    Robert Bell ·

    It depends what outcome

    It depends what outcome you're after. If you have a sequence of duplicated sections for repetitive work then loading one section with your resources, budgeted units and costs, then copying and pasting the activities could work?

    You can also assign resources to as many activities at a time as you wish by simply highlighting them first and then adding the resource(s) you want. This is quicker than line by lining it as often the works with the same resource will be grouped together by WBS or can be filtered on key wording or activity codes.

  3. 0
    Mohamed Civil ·

    Can yo tell me the method of

    Can yo tell me the method of loading resources by using Excel?

  4. 0
    Robert Bell ·

    You can do it by following

    You can do it by following the step by step guide here;

    http://www.toolboxforplanning.com/2012/01/how-to-import-activity-resource-data.html

    You need to export to excel first and then modify that file before re-importing it. You just have to be careful that the values you modify are recognised by the various dictionaries in P6 so these will need to be fully set up first.

    The other thing is you need the correct access rights (Superuser) to be able to Import XLS files. Otherwise you won't be able to do this.

  5. 0
    Zoltan Palffy ·

    create a resouce all it lump

    create a resouce all it lump sum

    default units/day would be 8

    make sure that calcluate cost from units is not selected

    filter for all activities

    select all activities (make sure that they are highlighted)

    right click assign resource select LUMP sum

    done

    now select file export

    select xls excel

    export resources and resouce assignments 

    modify the export to include resouce name, resource type, resource id, budgeted units and budgeted costs

    export to excel and populate the correct uits and cost in excel

    save file

    import form excel 

    select resource assignments

    import the excel file.

    if the info does not import run a global change

    where

    calculate costs from units equal yes 

    calculate costs from units = no

    committ the changes

    done 

     

     

     

     

     

  6. 0
    Adab Azeez ·

    hello zoltan palffy I tried

    hello zoltan palffy 

    I tried to import one excel file but it is not showing the destination to which it was supposed to be be imported. the window shows the following page. (please see the image). hope you would help me reach at some result.

    Thanx in advance.

     

  7. 0
    Zoltan Palffy ·

    make sure that the project is

    make sure that the project is open and you can not modify any columns or heading in the excel file only the data. Also anyt columns with and * asterick can not be imported. 

     

    also make sure that you have the proper rights to import the resource this is in the adminstrative portion under Admin

    Security profiles

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?