Collapsing and Expanding Sub Projects

Emma LangMember for 10 years 2 months
Created
2
2
0

I'm trying to collapse some but not all of the sub projects I have. Group and sort does it to a certain level, but is there a quick way to select a number of sub projects and expand or collapse them without having to affect the whole schedule?

 

Thanks

2 replies

Oldest first
  1. 0
    David Kelly ·

    All you have is "Collapse

    All you have is "Collapse to". So if you need to open up some rojects that are at Level 1 and other at level 4 and none in between you will be doing a LOT of clicking. 

  2. 0
    Zoltan Palffy ·

    you have 2 optionsoption

    you have 2 options

    option #1

    you can filter your projects that you want to collapse and expand 

     

    option #2 

    you can create a Project Portfolio and put the projects in there that you want to collapse and expand

Log in or join to reply