No Admin Option in P16.1 ?

Zahid ShaikhMember for 10 years 1 month
Created
2
2
0

No Admin Option in P16.1 ?

can anyone Guide me please

2 replies

Oldest first
  1. 0
    David Kelly ·

    The windows client

    The windows client reconfigures itself depending on the version of the database you install it to.

     

    With the EPPM database all of the admin tools are ONLY available in the web client

    With the PPM database you get the Admin pull down.

    No way round this......... Enjoy!