Updating task and resource allocation in P6 16.1
- Created
- 0
- 2
Hello Planners,
Let's talk about Activity A, "Task dependant", on which Resource A is being allocated; duration is 5 days, budgeted units are 40h.
Project is set to recalculate allocation actual units and cost when actual duration changes.
I am updating the activity by %Duration.
When Task Duration is "Fixed duration and units" or "Fixed duration and units/time", updating the activity to 50% will set the actual and remaining units to 16.
When Task Duration is set to "Fixed units" or "Fixed Units/time", updating the activity to 50% will set the remaining units to 16, but let the actual units to 0.
Can somebody explain this behavior? Does P6 have somewhere a new functionality that I have not discovered yet?
Thank you,
Alexandre
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?