Resource Assigning

Mujtaba SalehiMember for 10 years
Created
4
2
0

Usually, Project manager or Site Safety are on site from the start of project. we make a resource for Project manager. how can we assign this resource to activiteis? should i add it for all activiteis?  

4 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    Create LOE (hammock) activity

    Create LOE (hammock) activity that lasts from the site work start to site work finish and assign project manager, site safety and others who shall be on site all the time there, not on project activities that shall be done by project workers. 

  2. 0
    Mujtaba Salehi ·

    Thanks for your

    Thanks for your Information. 

    how about its complition percentange? i mean, according to which items should i put the percentage? 

  3. 0
    Mujtaba Salehi ·

    Thanks for your

    Thanks for your Information. 

    how about its complition percentange? i mean, according to which items should i put the percentage? 

  4. 0
    Zoltan Palffy ·

    as VAl said create a new

    as VAl said create a new activity call it what you want for the activity type make it a level of effort

    make its predecessor a ss relationship to the very first activty in the schedule.

    make its successor a FF relationship to the last activity in the schedule

    assign a resource to the LOE activity

    make sure to ASSIGN A RESOURCE CURVE to the Level of effort activity or the total manhours or cost for that resouce will be distributed only on the 1st day of that activity.  

Log in or join to reply