Hi everyone,

I'm trying to make a simple report showing the budget for each WBS.

Is there any way to show a total for everything?

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    add the column for total

    add the column for total budget 

    go to group and sort 

    sort by wbs at to select show grand total

    then select view collapse to then select what level of wbs that you want to roll up to 

  2. 0
    David P ·

    Hi, thanks for the reply.I'm

    Hi, thanks for the reply.

    I'm not sure if I'm missing something but I do cannot see a column for total budget.

    In the report wizard, I choose WBS as the Selected Subject Area, in the column chooser there is Original budget, Current Budget, Proposed budget etc but no total.

  3. 0
    Zoltan Palffy ·

    under cost it is Budgeted

    under cost it is Budgeted toal costs under units it is Budgeted total units 