Error when updating Remaining Units / Time
In the Open Standard
Bellota CastanedaMember for 10 years
- Created
- 6
- 4
0
Hello,
I'm trying to update the Remaining Units/Time in the Resource Activities in my schedule. I have done an export, update the file and when I import I get the following message:
Error: Cannot assign the same Resource: RSRC: xxx to TASK ActivityID: xxx, Project: xxx more than once
However, I do not want to add the same resource twice, I just want to update the Remaining Units/Time (h/d) column on the already existing Resource.
Any ideas??
-B
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?