Removal of Constraint Issue

Ijaz AhmadMember for 20 years 3 months
Created
1
4
0

Hello Guys,

I am using Primavera version 8.2. I am having issue with the constraint date removal. When I remove some contraint on a finish date and set it to none, I still see a star beside the finish date and the late finish date still show the constraint date which I previously set while applying the constraint. Did any body notice this problem? Any solution will be highly appreciated.

Thanks

Ijaz

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    1. did you recalcualte the

    1. did you recalcualte the schedule ?

    2. is this activity linked to another activity in a DIFFERENT project. If so the * will stil be there 

Log in or join to reply