Converting Activity Codes to WBS in P6

Muhammad IqbalMember for 11 years 9 months
Created
5
2
0

Hi all,

Is there a way to convert Activity Codes to WBS in P6. I have searched and some people suggested to use SDK. First i dont know what SDK is and i dont have that too? 

I would appreciate if anyone could suggest the easiest way to convert.

 

Thanks,
Naveed

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    sdk stands for software

    sdk stands for software development kit this come with p6. Almost every program as a sdk that they make available to developers of other software in this case sdk will be used inconjunction with excel. 

  2. 0
    Muhammad Iqbal ·

    Thanks Zoltan,Can you further

    Thanks Zoltan,

    Can you further explain how i can use that in my perticular case?

    Thanks

  3. 0
    Zoltan Palffy ·

    you install sdk then you use

    you install sdk then you use the excel spreadsheet. Then sdk bridges the gap or is the interface between the spreadsheet and P6.

    So in the spreadsheet you can select your project and you have the get button and the set button

    the get button is like export in p6 and the set button is like the import function in p6

    so you use the get button to export your info from p6 change it or populate it then you select set to import it back into p6  

    you can do this for several different categories. 

  4. 0
    Binh Vu ·

    Someone can more detail

    Someone can more detail explain for us how to use SDK to convert Activities code to WBS.

    Thank you so much

    p/s: Video is better :D

  5. 0
    Zoltan Palffy ·

    open  the excel file

    open  the excel file dictionary6s.xls 

    type in the password

    select update project list 

    then select your project

    then select GET Activity Codes

    now copy these codes

    now open the wbs.xls file

    and type in the password

    select update project list 

    then select your project

    then select GET WBS

    now copy the codes from the other spreadsheet into the wbs spredshsheet 

    now in the wbs spreadsheet select SET WBS

    done

     

Log in or join to reply