Replace Resource without change in Budget Units / Time

Clement MarioMember for 9 years 11 months
Created
2
2
0

How do I replace a Resource without change in Budget Unit / Time either by using the "Replace" function or "Global Change"?

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you would have to ADD another

    you would have to ADD another resouce then run a global change to make them equal then delete the original resource 

  2. 0
    Clement Mario ·

    Zoltan Palffy,Thank you for

    Zoltan Palffy,

    Thank you for the suggestion, will give it a try and update you.