at completion duration issue
In the Open Standard
Umit TimuMember for 10 years 6 months
- Created
- 1
- 3
0
Hi Folks
Im importing same xer file into enterprise and into standalone version of p6
Im getting different dates&floats when scheduling with retained logic
when investigating reason, i saw that at completion durations are different for some in-progress activities , but all settings are same on both platform. I couldnt find out why
Any ideas?