at completion duration issue

Umit TimuMember for 10 years 6 months
Created
1
3
0

Hi Folks

Im importing same xer file into enterprise and into standalone version of p6

Im getting different dates&floats when scheduling with retained logic

 

when investigating reason, i saw that at completion durations are different for some in-progress activities , but all settings are same on both platform. I couldnt find out why

 

Any ideas?

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    2 possibilities 1. go to edit

    2 possibilities 

    1. go to edit users preference look a the time units and look at the Hours per Time Period.

    2. it is using the gloabl calendar instead of a project calendar and the two global calendars are different. 

Log in or join to reply