Ant PirMember for 13 years 4 months
Created
1
2
0

Hi,

Somone kow the procedure how open a program saved p6.4  with  a release p6.3

Regards

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    go to windows

    go to windows explorer

    highlight the xer file 

    right click and select open with then choose note pad or word pad

    in the first line of the file chnage the numbers from 6.4 to 6.3

    save file

    import file