quick question about copy and paste
In the Open Standard
Miles GoodchildMember for 9 years 9 months
- Created
- 11
- 6
0
Quick question as I don't have Primavera I can't answer a simple question: Can you copy and paste a simple table showing the items below out of Primavera and into Excel?
Many thanks
A reference (user entered number 1-200)
Name
Start
Finish
Basline Start
Baseline Finish
RAG (user entered - Red, Amber, Green, Complete)
% complete
Status date for the plan
Milestone (is this item a milestone - system generated I assume)
Critical (is this item on the critical path - system generated)
Plan name
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?