Longest Path
In the Open Standard
Kannan CPMember for 18 years 4 months
- Created
- 6
- 3
0
Hi,
I have a detailed schedule which represents the works of 4 packages. Each package WBS has it own work packages and activities.
I was trying to take the longest path of each package, by filtering each package and selecting also the longest path filter. But its not working. I dont want to select the critical path filter as it includes all the activities as per the settings of the critical path.
Is there any solution.
Best Regards
Kannan
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?