Matching the resource loaded MSP Schedule with Resource loaded P6

Rajkumar SMember for 14 years 11 months
Created
8
2
0

Hi friends, My MSP Schedule is matched with P6 schedule in terms of duration, Pre & Suc, leads & Lags, resources, calendar. Without leveling the resource, the both MSP and P6 is matched 100%. When enabling the level resource option in Both, P6 dates are not matching with MSP. I need P6 has to match with MSP. Because, MSP is finalized with client. I need to find which option to be enabled in P6 in order to keep the date matched with P6. I am breaking my head for past 2 weeks. Please give me a hint to resolve this. if require, I shall share the files to check the issues. My Mail Id: rajkumars2810@gmail.com. Regards, Rajkumar

8 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    1. Check your durations turn

    1. Check your durations turn on the decimals they may be different.

    2. Check you TIMES go to edit users preference and turn your TIMES on 

    3. Check you work TIMES in your calendar.

    4. Check you Data date TIME.

    5. Make sure that you are using a project calendar as opposed to a global calendar and that the calendar matches MSP exactly.

  2. 0
    Tom Boyle ·

    I think there is no solution

    I think there is no solution for your problem.

    The available leveling options for MSP and P6 are very different and cannot be perfectly aligned.  In addition the leveling rules for MSP are essentially a black box.  You may be able to introduce some preferential logic into your P6 schedule to mimic the MSP leveling decisions.  Even if you could get perfect alignment between the two tools in a baseline schedule, this alignment would disappear at the first update. 

  3. 0
    Zoltan Palffy ·

    Tom is correct they will

    Tom is correct they will NEVER match 100% get them as close as possible and then adjust accordlingly.

  4. 0
    Rajkumar S ·

    Hi,Thanks a lot for

    Hi,

    Thanks a lot for your valuable informations.

    I would follow the schedule with resource either with MSP or P6.

     

     

  5. 0
    Rafael Davila ·

    Resource leveling using

    Resource leveling using different calculation engines is a sure way to create mismatches, for this reason using different software to manage schedule and to manage risk does not makes much sense.

    The differences can be very big.

    https://www.stottlerhenke.com/wp-content/uploads/2011/09/2009-10-01_Aurora_WhitePaper_Turnaround.pdf

    • In this paper we have shown that resource constrained schedules and therefore resource constrained project management is greatly affected by the underlying resource-leveling / scheduling engine more so as the project becomes larger and includes larger numbers of resource requirements and other non temporal constraints. It is unfortunate that project teams that have put in the significant effort and cost to create a resource constrained model may not know that they could potentially reap huge time and cost savings simply by running there already built model through a different scheduling engine.

    By the way if using Spider Project out of the box, without need to look for prioritization rules we get better results than Aurora, P6 and MSP on the eight activities sample schedule, we get the optimal solution.

    Aurora01 photo Aurora_zpsospvtyvp.jpg

  6. 0
    Rajkumar S ·

    Friends,Thank you so much for

    Friends,

    Thank you so much for you prompt reply.

    I understood there is always differences in resource calculations of MSP and P6.

    Now i need to proceed with P6 in order to maintaining single control tool of project

     

     

     

  7. 0
    Rajkumar S ·

     

     

     

  8. 0
    Zoltan Palffy ·

    that would be your best

    that would be your best option