Resource Id's not importing from SubContractor Schedule
In the Open Standard
Nathanial Wheeler-HartMember for 13 years
- Created
- 1
- 2
0
Hi,
I am importing an updated schedule into our EPS and since the last update, I am not getting any Resource Id's. Budgeted Hours are fine, just no res. id's.
Always importing as a new project, and previously did not have this issue. Contractor has provided export in v7.0 and 8.3 to no avale. Even the large full export has not worked. Have tried multiple options in the import layout.
Feel like I am missing something silly here!
Thanks.
Nathanial
1 reply