How to access primus solution prim39021?

Emmanuel CruzMember for 12 years 9 months
Created
1
3
0

Hello,

I am trying to solve a problem in P6 and everytime I do a google search it points to primus solution prim39021, but I can't find this on oracle support. Does anyone know where to look for it?

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    Does this occur when you try

    Does this occur when you try to import EPS-level Activity Codes ? If so the Activity Code must already exist in the EPS node you are importing into as well as be assigned to an activity, or any higher EPS nodes in its hierarchical branch.

    This includes its parent nodes and the parents of its parent node etc... going all the way up to its respective root EPS node. You may also want to check  and make sure that the codes are not secure codes.
     

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?