Cross-schedule Critical Paths

Ashley GreatorexMember for 12 years 11 months
Created
3
2
0

Hi all,

I was just wondering if it is possible to see cross-schedulecritical paths; e.g. if I have a project split into 3 schedules, which are linked together with inter-project dependencies, is it possible to see 1 critical path for the whole thing?

Thanks,

Ash

3 replies

Oldest first
  1. 0
    David Kelly ·

    This is one of the scheduling

    This is one of the scheduling options. 

    1) when you open more than one project, the scheduling options for the group are determined by the "Default project" (set under the Project main menu tab)

     

    2) That Default project should have the "Calculate Total Float" option set for "Opened Project"

     

    You now have a single scheduling entity, no matter how many projects are open

  2. 0
    David Kelly ·

    This is one of the scheduling

    This is one of the scheduling options. 

    1) when you open more than one project, the scheduling options for the group are determined by the "Default project" (set under the Project main menu tab)

     

    2) That Default project should have the "Calculate Total Float" option set for "Opened Project"

     

    You now have a single scheduling entity, no matter how many projects are open

  3. 0
    Zoltan Palffy ·

    there are two optionsoption

    there are two options

    option #1

    filter for longest path 

    option #2

    create a global code call it Mypath

    make the code value MP for my path

    add this column to the view

    filter for the last activity in the schedule 

    look at its predecessors and look for the one that is checked DRIVING AND CRITICAL

    now in the predecessor window highlight that activity and then click on GoTo

    keep doing this until you get back to the data date or the start of the project.

    now in the column that you just added (MYPATH) put in the code MP

    now do a fill down for all of the activities that are on your screen

    now filter where Mypath equals MP

    now you have it 

     