Sorting Individual WBS levels

Kyle SMember for 10 years 7 months
Created
3
1
0

I am attempting to aplly different sorting parameters to individual WBS levels rather than sorting the entire scedule with a single sorting parameter.  Is this doable? 

3 replies

Oldest first
  1. 0
    David Kelly ·

    The short answer is no. A

    The short answer is no. A sort parameter only applies to the whole Layout. But within the WBS window you can promote or demote individual WBS values within their parent value. So one WBS code at a time you can determine the sort order of an activity layout grouped by WBS.

  2. 0
    Rafael Davila ·

    WBS STRUCTURE 1You re-group a

    WBS STRUCTURE 1

    WBSX1 photo WBSX1_zpsymiwjsnh.jpg

    You re-group a WBS structure by creating a new one.

    WBS STRUCTURE 2

    WBSX2 photo WBSX2_zpsh2pqns9x.jpg

    You can sort any WBS structure if using sorting by columns/multiple columns and using a User Defined Field to enter sort values at the WBS bands/rows.

    WBSX2.1 photo WBSX2.1_zpslycieggc.jpg

     

    WBSX3 photo WBSX3_zps981wti0i.jpg

    Needless to say you can create a nes WBS structure for every sorting of your choosing.  Another option might be to fill all rows, WBS bands as well as activity rows and use this single column for your sorting.

    I do not believe P6 will allow you to create multiple WBS structures but it shall handle some WBS sorting if using sort by columns.

  3. 0
    Zoltan Palffy ·

    you can group by wbs then

    you can group by wbs then sort by something else within the grouping. If you want a finer and more flexiable grouping and sorting capabilities I would sugguest that you create activity CODES and assign the proper activity codes to the activities. 

Log in or join to reply