Hi Everyone,

 

Has anyone found a way to display individual resource assignments in Activity View Gantt chart?

 

I have Group & Sort as by Resource, but activities that have multiple resources are grouped together as if they were a single resource. Is it possible to Group the individual assignments in the Activity Tab?

 

Rod

6 replies

Oldest first
  1. 0
    Santosh Bhat ·

    Not in the Activity Tab, but

    Not in the Activity Tab, but this can be done in the Resource Assignments view.

    Think of it this way:

    • In Activity View, each activity is only displayed once, 
    • In Resource assignments view, each resource assignment is only displayed once, 

    And in the Assignments view, you have options to group, sort filter and display columns just like in the activity view (

    You can see what can be presented on this page I wrote some time ago: Primavera P6 Views and Layouts | Australasian Project Planning (austprojplan.com.au)

  2. 0
    Alex Lyaschenko ·

    Rodney,As a list, it could be

    Rodney,

    As a list, it could be done via Resource Assignments. Santosh explained it well.  If you ask about the resource Gantt Chart, Primavera can't do it. You need to export your schedule to another tool. At least Spider Project has Resource Gannt

    https://saluteenterprises.com.au/spider-project-product/spider-project-advanced-resource-modelling/

  3. 0
    David Kelly ·

    You could use Primavera P3

    You could use Primavera P3 from about 1985 ?

     

    You could:

     

    Export a spreadsheet with the Activities sheet which has an extra blank text UDF, and the Resource Assignments

    Concatenate the resource assigments into the Activity Sheet UDF

    Import the spreadsheet

    Use the UDF as a barchart label

    Luckily, offspring #4 is an Excel guru, and I get this stuff done very quickly!

  4. 0
    David Kelly ·

    You could use Primavera P3

    You could use Primavera P3 from about 1985 ?

     

    You could:

     

    Export a spreadsheet with the Activities sheet which has an extra blank text UDF, and the Resource Assignments

    Concatenate the resource assigments into the Activity Sheet UDF

    Import the spreadsheet

    Use the UDF as a barchart label

    Luckily, offspring #4 is an Excel guru, and I get this stuff done very quickly!

  5. 0
    Rafael Davila ·

    Materials are consumable

    Materials are consumable resources that must be available ("leveled") in order for the schedule to be viable. If materials become depleted activities can be interrupted until more become available.

    Material Gantt among other things can show:

    • the activities for each material as well as the activity interruptions
    • diagrams that show inventories level and materials consumption rate
    • parameter values for materials available in this view but not in Activity Gantt.

    2022-10-22-08-09-18

    Rarely my jobs are limited by materials to the point materials leveling is necessary.  In rare ocassions when materials must be leveled in our jobs these are frequently a driving constraint. It may seem an exageration to level materials easily available such as cement and sand but in remote location these can become critical.

    2022-10-22-17-05-43

  6. 0
    Rafael Davila ·

    Spatial resources cannot be

    Spatial resources cannot be modeled as Renewable Resources. Spatial resources we model as consumable resources, therefore we track them using Materials Gantt.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?