Created
10
2
0

Hello,

P6 has a default 8hrs/day (Hours/Time period). If we create a calendar of 10 hrs/day, the duration gets affected because of the default 8hrs/day. What's the best way to fix this.

 

Regards,

SAN

10 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    go to edit users prefrence

    go to edit users prefrence look under the Time Unist Tab and make sure that they match your calendar

  2. 0
    Tom Boyle ·

    Assuming you have properly

    Assuming you have properly set the Hours per Time Period in your 10-hour calendar ("Time Periods" command), then go to Admin Preferences/Time Periods/Hours per Time Period and check the box for "Use assigned calendar to specify the number of work hours for each time period."

    Alternately, you could change the default values in the Admin Preferences.

  3. 0
    san TS ·

    Thank you. Regards,SAN

    Thank you.

     

    Regards,

    SAN

  4. 0
    Zoltan Palffy ·

    glad we could help

    glad we could help 

  5. 0
    Naseeb KP ·

    Hi friends,I need a help of

    Hi friends,

    I need a help of the similar kind. I have an 8 h/d calender assigned to my project, but with an exception of 6 h/d assigned to one month in between. But for every activities that come along with and after the exception dates are showing problems in their start dates. For eg: for all the FS relations the successors are supposed to start one day after the finish date of the predecessor, but the successor is tarting on the same date the predecesso ends. Also when i give a lag on the activity resource asssignment by say 3 days on the days of exceptions, the start dates shift by 4 or 5 days. I cleared the later problem by giving lags in fractions. 

    How can i rectify such problems? Will this happen whenever there is an exception to the claender? 

    PS: I am new in planning. apologies if my question is a blunder

    Thanking you in advance

    Regards

    Naseeb

  6. 0
    Zoltan Palffy ·

    Naseebgo to tool schedule

    Naseeb

    go to tool schedule then options

    at the bottom change the calendar for scheduling relationship lag to

    Successor activtiy calendar  

  7. 0
    Naseeb KP ·

    Dear Zoltan,Thank you for

    Dear Zoltan,

    Thank you for your support. I tried ur lead. But its not working. The dates are the same. i.e., the start date of the successor and the end date of the predecessor are the same for FS relationships like in mentioned in my previous comment.

    Regards 

    Naseeb

  8. 0
    Naseeb KP ·

    Dear Zoltan,Thank you for

    Dear Zoltan,

    Thank you for your support. I tried ur lead. But its not working. The dates are the same. i.e., the start date of the successor and the end date of the predecessor are the same for FS relationships like in mentioned in my previous comment.

    Regards 

    Naseeb

  9. 0
    Naseeb KP ·

    Dear Zoltan,Thank you for

    Dear Zoltan,

    Thank you for your support. I tried ur lead. But its not working. The dates are the same. i.e., the start date of the successor and the end date of the predecessor are the same for FS relationships like in mentioned in my previous comment.

    Regards 

    Naseeb

  10. 0
    Zoltan Palffy ·

    change the calendar that the

    change the calendar that the activity is on