Remaining Total Cost Distribution
- Created
- 9
- 2
Hello everyone,
I have an activitiy (not started) which is scheduled to start in 29 March 2017 and finish in 08 May 2017. However, when i chect the remaining total cost layout, it shows the total cost only in May 2017. It does not distribute the cost evenly.
I do not have any curve assingned to that resource.
Calculation settings which are checked:
Link budget and At Completion for not started activities
Reset remaining duration and units to original
Substract actual from at completion
Recalculate Actual Units and cost when duration % changes
Link actual to date and actual this period units and costs
Regards.
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?