Primavera P6
In the Open Standard
Ranch DobankMember for 9 years 7 months
- Created
- 2
- 1
0
I've been using Primavera P6 for a few months now and I notice that the time of finish for different ativities turns out to be different even when I check them all off as complete at the same time. Is there some setting with respect to time that I'm missing somwehere?
For Example, if I used a data date of March 8 and checked off complete for two different activitie before I scheduled, one would show completed at 6.00PM and the other would say 4.00PM. I've seen multiple timings like this.
Suggestions would be greatly appreciated.
Thanks.