Particular Resource assignment automatically in Primavera among the group of Resources

Rama ChandranMember for 14 years 10 months
Created
3
3
0

Hi

Need your support here.

This is related to Manufacturing planning works.

Activity A (Machining operation) - 15 days

Activity B (Machining operation) - 10 days

Activity C (Machining operation) - 20 days

Activity D (Machining operation) - 25 days

Activity E (Machining operation) - 5 days

Activity F (Machining operation) -  5 days.

 

All above activities were independent. We are having two resources say LATHE 1 and LATHE 2. Is is possible in Primavera , assigning a resource (either LATHE 1 or LATHE 2) automatically based on the resource availability to get better results (Shortest Project duration).

 

Thanks in advance

Ram

3 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    This is called Skill

    This is called Skill Scheduling.

    I also expect that your resources may have different production rates and that you would like to use norms and measure your works in physical units, etc.

    If you need this functionaity try Spider Project.

  2. 0
    David Kelly ·

    Rama, Primavera has no

    Rama,

     

    Primavera has no mechanism for automatically assigning resources. 

  3. 0
    Zoltan Palffy ·

    no

    no