Skip to content

how to asign multiple activities to a wbs?

Ahmet TuterMember for 13 years 8 months
Created
4
2
0

is there a shortcut to assign multiple new activities i created to a wbs all at once? one by one is taking too much time

4 replies

Oldest first
  1. 0
    Rama Chandran ·

    Select the activities

    Select the activities (Ctrl+Activity).

    Move the cursor to the left side of the activity table. Cursor with small rectangle appears.

    Now drag the activities to the needed WBS.

  2. 0
    Zoltan Palffy ·

    add a column for wbs do the

    add a column for wbs do the first one then do a fill down 

  3. 0
    Zahid Rehman ·

    I was looking for the

    I was looking for the solution of the same issue since last one week but in vain.... Thanks Chandran , this tip really worked...

  4. 0
    Zoltan Palffy ·

    2 optionsoption #1if you can

    2 options

    option #1

    if you can get your activities lined up or group another way then you can add a column for the wbs and then do the 1st one and then do a fill down

    option #2

    you can export the activites to excel when you export them if they have not been assigned they wil automatically  take the wbs of the project id that is the highest level. You can then change them in excel and import them back into p6

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?