START AND FINISH MILESTONES ARE NOT SHOWING IN MY ACTIVITY TABLE

Michael AkinleyeMember for 9 years 6 months
Created
3
4
0

Hello Everyone,

Please i need an urgent assitance, in my activites table My Start are finish milestones are not showing, Including my Project start and finish date, Has anyone come across this before? 

Please i need an assistance on how to fix it 

Thanks in anticipation

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    filter for all

    filter for all 

  2. 0
    Michael Akinleye ·

    Thanks Alot

    Thanks Alot 

  3. 0
    Zoltan Palffy ·

    I get this all of the time.

    I get this all of the time. My milestones are gone or all of my activities are gone. No it just a filter being applied.

Log in or join to reply