Scheduling Activities Just in Time for Its Successor
In the Open Standard
Sha ShajihanMember for 10 years 9 months
- Created
- 3
- 2
0
I have equipment procurement activities that need to be delivered just in time for each install. I place all the orders on Day 2 of the project. I want to show, for each equipment, a lead time extending upto its install activity (its successor) starting on Day 3 upto Day X where X varies depending on the equipment.
I am using P6 R16.2. Using the ALAP constraint is an option, but using it for 15 activities?
Any suggestions is most appreciated.