P6 DURATION FROM MANHOURS

Zax CudMember for 11 years 4 months
Created
2
1
0

I developed a schedule from Jobcard, inputted the Resources and Manhours of each activities into the P6 with a daily Work  productive time of 8hrs /day and 7day work week . What am looking for, is there a way the duration will automatically come up based on the information I have provided?

2 replies

Oldest first
  1. 0
    Pankaj Mishra ·

    Hey Zax, In case of P6, its

    Hey Zax,

     

    In case of P6, its not possible , but if you want automatic duration comes then you will try to make a project in Microsoft project and save baseline and update automatically come when you'll putting actual time.

     

     

     

    thanks

  2. 0
    Zoltan Palffy ·

    yes make sure that the

    yes make sure that the duration TYPE is FIXED UNITS/TIME

    this way when the budgeted manhours change the durations will change.