Resource creation & assignment
In the Open Standard
Mike ReymortMember for 9 years 4 months
- Created
- 1
- 2
0
I would like to know what is the criteria for creating resources in terms of maximum units per time. If I set a resource for 1h/d it means that I am going to load it based on manhours required for the activity (Not sure if this method is correct or not). If I set the resource for 8h/d then I should load it against actual man-days required for the activity. My question is, which is the correct method? Or if both are wrong what is the correct one.
Thanks in advance !
Mike
1 reply
Oldest firstLog in or join to reply