Exporting from P6 16.1 to MSP 2010

Emma LangMember for 10 years 2 months
Created
5
4
0

Hello, 

What is the easiest and quickest way of exporting from P6 to MSP without dates and hours looking mental? I've tried doing a straightforward export but a lot of my dates have changed, even for completed activites, and the work is also incorrect?

Any help would be appreciated. 

Thanks

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    try the html methoddoes not

    try the html method

    does not matter what you do they will never match the way msp handlesa wbsis different,  calendars are different, the alogrithm calculation for the forward and backward pass is different, the way MSp handles milestone is different. Just be glad that you do noy have to type the activities again

  2. 0
    Emma Lang ·

    Hi Zoltan, Can you explain

    Hi Zoltan, 

    Can you explain the html method?

    Thanks

  3. 0
    Zoltan Palffy ·

    sorry I meant XML

    sorry I meant XML

  4. 0
    Emma Lang ·

    ah.. thanks. Tried that

    ah.. thanks. Tried that yesterday, dates were all over the place. 

    Looks like I'll need to check the dates of 2000 activities line by line

    Thanks anyway

     

  5. 0
    David Kelly ·

    The only safe way to do it is

    The only safe way to do it is to use Collabro's Legare software. 