Resource Usage Profile - Baseline
In the Open Standard
Emma LangMember for 10 years 2 months
- Created
- 7
- 3
0
Hello,
Is it possible to show the baseline in the resource usage profile in order to show a comparison? All I can see is the budgeted units, actual units etc?
I'm looking to use this in order to show how certain changes have impacted the schedule and how the man hours have changed since.
Also, is there a way to put the number of hours per month or week on the graph, i.e below the month? I know this can be done in MSP but I've not found the correct setting in P6 yet (if it exists).
Thanks
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?