a) Regarding ‘How can I do progress off in my whole project?’ means that I assigned the progress to the activities in Performance % complete column. Now I want to remove/clear
What I think you really mean here is how do I destaus my my schedule ?
How to de-status a schedule
1. Choose Enterprise, Projects and select the Calculations tab. Choose to "Link Budget and
At Completion for not started activities" and "Reset Remaining Duration and Units to
Original
2. Choose View, Columns and add the columns for Actual Labor Units, Actual Nonlabor
Units.
3. Choose Tools, Schedule and set the data date equal to the Project Start Date and schedule.
To find the Project Start date, choose Enterprise, Projects. Click on the Dates tab and
note the Planned Start date.
4. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities in
this column and choose Edit, Fill Down.
5. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activities
in this column and choose Edit, Fill Down.
6. Choose Tools, Global Change and run the 1st Global Change. This will set the Actual
Material Units to zero.
7. Run the 2nd global change which sets the activity status to Not Started.
1st Global Change:
Subject Area:
Activity Resource Assignments
If: Resource Type equals Material
Then: Actual Material Units = 0
2nd Global Change
Subject Area:
Activities
If:
Where Activity Status is not equal to Not Started
Then: Activity Status = Not Started
If this process is not used you may encounyter the error
"Cannot set Status to Not Started if activity has actuals
if so run the 3rd Global change
Add durations to activities by running thsi global change for Not Started Activities
Subject Arera;
Activities
If:
Where Activity status is equal to Not Started
Then:
Remaining Duration = Original Duration
b)Secondly how to change color of shaded area of Non working days plotted on bar chart? How to do that
if you go to time scale and seclect the date interval of Week/day the non working days should be greyed out