Milestone Points on Gantt Chart

Adam CollinsMember for 14 years 8 months
Created
1
2
0

Hello 

I am wanting to set marker points/milestones along the activity line for procurement for a high level tender schedule in P6. I have done this before some time ago using dates in the user defined fields to capture the dates (ie: Bid Submission / PO Award / Delivery). 

Has anyone else done this before and can offer some assistance? 

 

Thanks

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    why not create a unique code

    why not create a unique code for the activities that you want to show then assign the code value to each of theses activities then filter for that code 