Skip to content

Percent on Completed Miestone Activity

Katie CoombsMember for 13 years 3 months
Created
1
1
0

Hi,

I have a schedule with milestone activities that are complete but are showing only 0% complete.  It is only happening to some of the milestone activities and not others.  Percent complete type is Physical, its a start Milestone and both started and finished boxes are ticked (actualized).

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    when you say showing 0%

    when you say showing 0% complete is that physical or duration % complete

    look at the duration type what is it ?

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?