Performance % Complete

Sebouh PamoukianMember for 17 years 8 months
Created
1
1
0

I received a scedule update using performance % complete in a schedule without resources. Does that make any sense? Isn't performance percent complete related to EVM? How can P6 show PPC when there are no resources in the schedule?

Thank you

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    yes the Performance percent

    yes the Performance percent complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far.

    since there are no resources Ttis just means that there will not be an earned value calculated. You can still have a performance % complete if you look at the duration % complete or the activity % complete  I bet they are the same numbers as the Performance % complete numbers.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?