Dear All,
I have a schedule in Primavera P6 that which the Periods were never stored. We update this schedule on a weekly basis, and now we are in week 135. We are having issues with some stakeholders. The progress curve, which uses de P6 data, has variations on the later weeks, due to the variations in units distribution for "in progress" activities.
The question is: What would happen if we start to use Store Period Performance from now on? Would we have to manually fill the past periods?
If so, is that any workaround we could use to make this job easier?
Regards.