Skip to content

Store Period Performance

Romeu Oliveira JúniorMember for 20 years 9 months
Created
1
1
0

Dear All, 

I have a schedule in Primavera P6 that which the Periods were never stored. We update this schedule on a weekly basis, and now we are in week 135. We are having issues with some stakeholders. The progress curve, which uses de P6 data, has variations on the later weeks, due to the variations in units distribution for "in progress" activities.

The question is: What would happen if we start to use Store Period Performance from now on? Would we have to manually fill the past periods?

If so, is that any workaround we could use to make this job easier?

Regards.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    is you started now would get

    is you started now would get one big dump of cost during this update

    you can manually fix this

    the work around is to use it from day 1

    this is how to edit store period performance

    To edit stored actual units or cost for a past period
     
    If you have already defined the financial period,
    Select Edit User preference
    Then select Application - at the bottom under column level- select the
    financial period for which you want to edit the past period performance of
    any specific resource assignment-then close
    Next go to the Activity mode
    Click the resource tab
    Right click on resource detail & customize-add columns from "Financial
    Period Value"- Press ok-
    Now in the Details window you can edit the past performance actual there.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?