Revised Program in P6

Ibraheem AkinMember for 13 years 5 months
Created
1
3
0

Hi Everyone.

I'm currently working on a Revised Program from the last update (in P6), and I've already adjusted and Corrected all dates and Relationships and even I've used Global Change to make Planned % Complete and Actual Percentage complete equal, it worked well for Enginerring, Procurement and Even Construction Stages, but 3 activities (2 from Pre-Construction Documentation and 1 key milestones (Contract period)) didn't change, which is affecting Overall % because the 3 actiities are being update using Physical % Complete, and if I change them to duration % complete it is affecting their actuals, which is affecting Overall % also (driving it back).......

 

Please how do I solve this kind of Issue withouth Changing it's % complete type to Duration??????

 

Thanks & Best Rgards.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    run a global changewhere

    run a global change

    where physical % complete is greater than 0

    then duration % complete = physcial % complete

    have you copied this schedule and made this your new baseline ?

    what is your earned value calculation setting ?

    Budgeted values with current dates

    At completion values with current dates 

    Budgeted values with planned dates