% Complete Column

Andy HudsonMember for 10 years
Created
3
1
0

Hi,

Please see attached screeenshot (http://ge.tt/7uuG97m2 ). . I previously used it in Asta.

Now I need your help to do so in P6:   

a) How to give Weekly planned % complete column and actual Weekly  % Complete column as I highlighled in rectangle?

b)How to show different weekly progress lines on bar chart at the same time as highlighted in screenshot?

Please advise.

Cheers

Andy

3 replies

Oldest first
  1. 0
    David Kelly ·

    Andy, P6 only roles up,

    Andy,

     

    P6 only roles up, indeed only stores % to date for current and baseline schedules. 

    A spreadsheet view of quantities forecast per week is simple, but expressing those as percentages is barely possible, making those percentages roll up is impossible.

  2. 0
    Zoltan Palffy ·

    for planned you have to have

    for planned you have to have a baseline attached 

  3. 0
    Andy Hudson ·

    Thanks Zoltan and Dave

    Thanks Zoltan and Dave