Multiple productivities in one activity
- Created
- 5
- 2
Hi,
I'm trying to set up a Primavera Project for a future sensitivity/Monte Carlo analysis, therefore, I need to automatize the current schedule.
I have two activities running in paralell. Activity 1 is shorter than activity two and once it finishes, its resource can go support Activity 2. Therefore, only when Activity 1 finishes, the progress rate of Acitivity two changes from R2 to R1+R2. Also, the works performed by R1 in Activity 2 require a third activity afterwards. This means that the units where R1 worked (R1*(T2-T1)) will have to be used in a new activity, 3, with a new resource (R3).
Is it possible to do in Primavera automatically, so when the progress rate of the resource change, so do the duration of all activities?
Thanks!