How to determine activities without predecessors or successor

Binh VuMember for 9 years 5 months
Created
3
2
0

Hello everyone,

Someone can help me, how to issue the report as below.
Thank you so much.

3 replies

Oldest first
  1. 0
    Tom Boyle ·

    In P6, F9. View Log.

    In P6, F9. View Log.

  2. 0
    Binh Vu ·

    Thank you so much.

    Thank you so much.

  3. 0
    Zoltan Palffy ·

    Tom is correct except that

    Tom is correct except that you have to first check the box thats says Log to file and give the log file a location to write to then you have to schedule the project then after that you can view the log file 