HI,

 

I having an issue when i add a new resource on to a activity, Primavera  zeroes all costs added on all previously added resource.

and re calculate the units. I hacve unticked the auto compute and calc costs from units for the resouce but still happens,

Any ideas how to stop that from happening?

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    2 things to check 1. make

    2 things to check 

    1. make sure that the duration TYPE is set to fixed duration & units/time 

    you might have to add the column for duration type change the 1st one to fixed duration & units/time then do a fill down for that column.

    2. go to the project directory make sure that your porject is highlighted click on calculations then in the lower left make sure that 

    reset remaining duration and units to original 

Log in or join to reply