Monthly Planned progress from P6 without Cost/Resource

Yahya KutarvadaliwalaMember for 11 years 5 months
Created
2
1
0

Dear All

i am working on epc project, our time schedule is not cost & resource loaded means only time schedule.

is there any ways/methods to determine monthly plan % ??

2 replies

Oldest first
  1. 0
    David Kelly ·

    Since you do not have any

    Since you do not have any costs or resources, the monthly planned per cent complete is one month.

  2. 0
    Zoltan Palffy ·

    although I do not recommend

    although I do not recommend this technique you can do it 2 ways

    1 way is strictly tiime based and the other way is to calculate when actiivities were planned to FINISH vs when or is they have finished

    send me your email address and I will show u how to do this 

    you can also use project tracker you can get a free trial here

    https://www.willmer.co.uk/

Log in or join to reply