Weird Problem in P6
In the Open Standard
Adab AzeezMember for 10 years 3 months
- Created
- 10
- 5
0
Mr. zoltan, I have prepared a schedule in primavera. That comprises a start mile stone, finish mile stone and in between these two mile stones there are 7 WBS having 4 activities each. Calender is 24X7 hrs. And all relationship type are finish to start.
I am wondered that after scheduling all my ghant chart bars are showing Red- red every where, i.e. entire project appears to be in critical path.
All activities are in FS relationship.
I think its wrong. Can you find the mistake ?
10 replies
Oldest firstLog in or join to reply