Weird Project Finish Date

Richard AMember for 12 years 3 months
Created
3
2
0

Hello Folks,

I am quite new here as a member, however I have been a pseudo member coming on and off before. I have a recent issue with my Primavera P6 V8.2 settings ( I suppose). What I have noticed is that, whenever I load up an XER file sent from a project member onto my PC, there are certain mile stones and regular activities that has the project 'finish date' changed. I always know immediately  that the dates are not the true dates especially when the xer file is a baseline schedule. However, whenever the same file is loaded on any other PC other than mine, the true real dates show up. I have varied my duration columns to troubleshoot this but still no luck. I will appreciate your help to decipher the 'date changing ghost' on my PC. 

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi RichardWelcome to Planning

    Hi Richard

    Welcome to Planning Planet.

    Check your calendar settings.

    Best regards

    Mike Testro

  2. 0
    Ahmed Aziz ·

    Hi Richard,Make sure that the

    Hi Richard,

    Make sure that the default calendar is a 7day calendar then hit (F9), i hope this will fix the problem.

  3. 0
    Richard A ·

    Ok folks, just to update you

    Ok folks, just to update you on the eventual solution to my initial post as it may end up saving someone's time one day.

    All I did was to go to Admin Preferences - Earned Value

    And under the Earned Value Calculation I chose 'At completion values with current dates' 

    Followed by an F5 (refresh)  and then F9 (Schedule).

     

    And that was it. All dates became conformed and showed correctly.

     

    cheers