Export into Excel - 'BL Project Physical % Complete'

Larry CahnMember for 8 years 10 months
Created
2
3
0

Hello all - My layout has the column 'BL Project Physical % Complete', however it appears P6 won't allow me to export this column as it doesn't show up as an option in the columns when exporting. With our reporting it would be very useful to show the previous/baseline physical % complete compared to the current physical % complete.

Does anyone know how to export the 'BL Project Physical % Complete' column into excel?

Thanks ahead of time.

2 replies

Oldest first
  1. 0
    David Kelly ·

    ...... any why will "Schedule

    ...... any why will "Schedule % compete" not do instead? It is baseline-based.......

  2. 0
    Zoltan Palffy ·

    ANYTHING that if you can

    ANYTHING that if you can display as a column you can export to excel

    display the column 

    select all of your data (edit selat all) 

    right click and select export to excel

    done 